Official window
2021–2030
Target year: 2030
Project status
This page summarises the second Gotthard tunnel project with calendar-based progress, remaining time, and the kind of technical numbers that tunnel geeks love.
Official construction facts: the 16.9 km bore advances at about 20 m/day per TBM on average, with around 680,000 m³ of concrete and 160,000 m² of green area mitigation.
The project phase for the second bore runs through 2030; the first bore is then scheduled for refurbishment from 2030 to 2033.
Official sources point to 2030 as the target year; no exact day/month opening date is published.
No. The percentage is the calendar progress across the official 2021–2030 build window.
The official project page cites an average of about 20 metres per day per machine.