Tweede Gotthardtunnel: hoe ver zijn we?

Deze pagina bundelt de voortgang van de tweede Gotthardtunnel met kalenderprogressie, resterende tijd en technische weetjes voor liefhebbers van tunnelnummers.

Officieel venster
2021–2030
Doeljaar: 2030
Kalenderprogressie
55,9%
Calendar progress across the official build window
Resterende dagen
1.610
Days until the end of the 2030 build window
Dagen sinds start TBM’s
538
TBMs started the main drive in February 2025

Handige nerdcijfers

16.9 km
official tunnel length
12.3 m
diameter
7.4 million t
rock to remove
68
cross passages approx.
126,6m CHF/km
project cost per km
423
days per half-bore at 20 m/day

Official construction facts: the 16,9 km bore advances at about 20 m/day per TBM on average, with around 680.000 m³ of concrete and 160.000 m² of green area mitigation.

The project phase for the second bore runs through 2030; the first bore is then scheduled for refurbishment from 2030 to 2033.

Belangrijk om te weten

FAQ

Wanneer opent de tweede Gotthardtunnel?

Officiële bronnen noemen 2030 als doeljaar; een exacte dag/maand wordt niet gepubliceerd.

Is de voortgang fysiek gemeten?

Nee. De percentagewaarde is de kalenderprogressie binnen het officiële bouwvenster 2021–2030.

Hoe snel gaan de boormachines?

Het officiële project noemt gemiddeld ongeveer 20 meter per dag per machine.